This month, we successfully executed and charged a 220kV AIS switchyard project for UltraTech Cement Ltd. (UTCL) for their greenfield cement plant at Petnikota in Andhra
Pradesh.
The scope of the project involved end-to-end supply, installation, testing and commissioning of two 220/11.5kV 25/30 MVA transformers, complete switchyard equipment, civil works, and securing CEIG (Chief Electrical Inspector to the Government) approval.
Despite the challenges of a remote hilltop site and daily 40 km commutes, the team delivered on time and to complete customer satisfaction, earning a completion-cum-appreciation letter from UTCL.